On a utility-scale plant, the same structure is repeated thousands of times. A small error on the first table becomes a big problem by the thousandth. This checklist covers the steps that keep installation fast, accurate and on specification.
1. Before mobilisation
- Approved structural drawings and design calculations are available on site
- The geotechnical report has been reviewed and the foundation type and depth confirmed
- Material received matches the bill of materials, coating specification and MTCs
- The storage area is level, dry and keeps material off the ground to protect coatings
2. Survey and layout
- Benchmarks are established and table positions marked as per the layout
- Row spacing is checked against the shading design
- Ground levels are recorded so post heights can be adjusted for uneven terrain
3. Piling and foundations
- Posts are installed to design depth and within verticality tolerance
- Pull-out or load tests are carried out on sample piles where specified
- Top-of-post levels are checked along each row before erection
4. Erection and alignment
- Rafters are fixed at the design tilt angle — verify with a digital inclinometer
- Purlins are aligned in a straight line along the row
- Bracing is installed as per drawings before modules are loaded
- No field cutting or drilling without engineer approval — it damages the coating
5. Fastening
- The correct bolt grade and coating are used at every joint
- Bolts are tightened to the specified torque, then spot-checked and marked
- Module clamps are placed within the module manufacturer's permitted zones
Pre-punched, roll-formed members with minimal site welding are one of the biggest time-savers on a fast-track project.
6. Inspection and handover
- A table-wise inspection record covers levels, tilt, torque and a visual coating check
- Any coating damage is touched up with zinc-rich paint
- As-built documents and QC records are handed over to the client